842 hours of new compute, and no capacity bought

An ERP go-live sent an analytics platform running hot. The question on the table was how much capacity to buy. The answer was a schedule.

Client
National automotive distributor
Capabilities
Technical advisory · Systems architecture
Status
Delivered

842 h

dev compute added in one week

81%

of it scheduled rebuilds colliding

0

capacity upgrades needed

01 / Context

A national distributor runs its reporting on Microsoft Fabric. A new ERP went live, and the analytics platform behind it started running hot the same week.

02 / Problem

The question on the table was how much more capacity to buy. Nobody could say which workloads were using what, because model rebuilds, batch loads and report queries all shared one lane and collided freely.

03 / Architecture

I treated it as an attribution problem before a sizing problem. Every hour of compute for the week either side of the go-live was assigned to a workload and an owner, per environment, so development and test could be read separately.

The target shape was three lanes: builds, loads and reports, each with its own schedule, and an approval step before a new scheduled model joins a lane.

Fig. 01 · Process, before and afterAutomotive

Before

SystemERP go-live
SystemOne shared lanebuilds, loads and reports collide
PersonCapacity ownersees a total, no cause
OutputBuy more capacity?

After

SystemQuery history
CheckAttributionhours by workload and owner
SystemThree lanesbuilds · loads · reports
OutputSame capacity

04 / Implementation

I read the query history for both weeks and wrote the attribution queries against it. One family of models accounted for more than a third of the increase in development. In test the driver was reporting reruns, so the two environments needed different fixes.

The recommendation was operational: separate the lanes, freeze new scheduled models until approved, and break up the worst overlap windows. Buying capacity stayed on the list as a fallback.

05 / Outcome

Development compute had risen 842 hours in one week. 81% of it was scheduled rebuilds colliding. The fix was lanes and schedules, and no capacity upgrade was needed.

06 / Technical details

Platform
Microsoft Fabric warehouse and capacity metrics
Method
Query-history attribution by workload, owner and environment
Handed over
The attribution queries as a playbook anyone on the team can rerun, and a runbook for the next time the numbers creep